Dysart Preschool
Description
The new preschool campus included offices, classrooms, parking, and site work. With one month of permitting delays pushing the construction start date to February 2006, the project finished just 10 days after the initially scheduled start date and still in time for school in August. Additionally, Concord was able to return $81,000 back to Dysart Unified School District.
Budget
$4,962,274
Size
32,000 s.f.
Owner
Dysart Unified School District
Architect
Gilleland Brubaker Architects